          Expansion of Qinshan nuke complex proceeds

          (Xinhua)
          Updated: 2007-12-28 22:23

          HANGZHOU -- Workers on Friday hoisted a 170-ton dome into place over the underground workshop that will house a third reactor at the second phase of the Qinshan nuclear power complex, the first commercial nuclear power facility in China.

          That step cleared the way for installation of a 650,000 kw pressurized water reactor at the nuclear complex, which is located in Haiyan, on the northern coast of Hangzhou Bay, Zhejiang Province, not far from Shanghai. The Qinshan complex has three phases, each featuring different types of reactor, some of which were from domestic suppliers and some from foreign manufacturers.

          Construction of another underground workshop for a fourth generating unit is also under way, according to Yang Lanhe, General Manager of Nuclear Power Qinshan Joint Venture Co. Ltd, investor of the second phase of the Qinshan complex.

          The first phase of the Qinshan facility was also the first nuclear power plant on the mainland built independently by domestic engineers. Construction on the facility began in 1985. The first phase featured a 300,000 kilowatt  prototype reactor with a lifespan of 30 years, which went online in 1991.

          The first phase of the plant, which suspended power generation for a fuel change starting on October 28, is to resume operation in January. The complex will see the addition of two more pressurized reactors, each of which is to have an installed capacity of 1 million kilowatts.

          The first phase has so far generated 31 billion kwh of electricity and produced 9.6 billion yuan ($1.28 billion) in revenue and paid 1.8 billion yuan in tax.

          The plant also has second and third phases. The second phase involves the plant where work was done on Friday. It has two functioning 650,000-kw units that began generating power in 2002 and 2004, respectively. The expansion of phase two will involve the installation of two 650,000-kw pressurized reactors. The expansion program began in April 2006. It will be fully completed and start power generation in late 2011.

          Through December 17, the second phase of the Qinshan nuclear plant had generated 8.5 billion kwh of electricity for 2007. When all four units are in operation, the second phase will be able to produce 18-20 billion kwh of electricity a year.

          The third phase houses two Canadian CANDU heavy-water reactors.



          Top China News  
          Today's Top News  
          Most Commented/Read Stories in 48 Hours
          主站蜘蛛池模板: 亚洲av成人一区国产精品| 日本一区二区精品色超碰| 亚洲精品宾馆在线精品酒店| 精品一区二区亚洲国产| 国产精品片在线观看手机版| 亚洲成A人片在线观看无码不卡| 无码人妻一区二区三区兔费| 国产欧美综合在线观看第十页| 美腿少妇资源在线网站| 日本一区二区三区黄色| 国产精品无遮挡猛进猛出| 国产精品色三级在线观看| 国产精品久久久久影院亚瑟| 免费人成再在线观看视频| 国产精品一二二区视在线| 中文在线8资源库| 一区二区三区成人| 亚洲一区二区三区国产精品| 亚洲日韩av无码| 亚洲中文精品一区二区| 免费看的一级毛片| 青青草一级视频在线观看| 人妻中文字幕精品一页| 人妻中文字幕精品一页| 日韩理伦片一区二区三区| 日韩国产中文字幕精品| 国内a级毛片| 久热这里只有精品12| 成在人线av无码免费高潮喷水| 伊人欧美在线| 亚洲成av人片在线观看www| 欧美不卡视频一区发布| 动漫av网站免费观看| 无人视频在线观看免费播放影院| 一区二区三区岛国av毛片| 亚洲精品香蕉一区二区| 国产精品一区二区三区91| 日本丰满少妇高潮呻吟| 免费无码中文字幕A级毛片| 亚洲色最新高清AV网站| 91麻豆国产精品91久久久|