          HK-mainland express rail faces new delays

          Updated: 2015-06-27 08:14

          By Timothy Chuiin Hong Kong(HK Edition)

            Print Mail Large Medium  Small

          Tien says problems with the canopy of the terminus may be to blame

          The Guangzhou-Shenzhen-Hong Kong Express Rail Link faces further delays and budget overruns, although work on the tunnels feeding Hong Kong's 15-platform terminus for the multibillion-dollar project has already been completed.

          Michael Tien Puk-sun, who chairs the Legislative Council's (LegCo) transport panel, warned on Friday that delays could be caused by problems relating to part of the West Kowloon Terminus' dramatic curved steel and glass-roof canopy.

          Quoting sources, he said the canopy could not withstand typhoon-force winds and rectifications might be needed.

          Contractors responsible for the construction of the roof may file a lawsuit against the designers - global architecture firm Aedas and engineering firm AECOM.

          Tien pointed the finger at MTR Corporation's management, accusing senior executives of turning a blind eye to attempts by the contractors to seek remedy.

          The corporation, which Tien once headed, says the glass-and-steel canopy meets design specifications, and had been approved by the government.

          The MTR board held a closed door meeting on Friday to discuss possible cost overruns. It will submit a report to the government early next week, Chief Executive Officer Lincoln Leong Kwok-kuen said.

          Independent non-executive directors, including lawmakers Abraham Shek Lai-him, Ng Leung-sing and Vincent Fang Kang, who also attended the meeting, were tight-lipped over what was discussed, while the government's four representatives on the MTR board stayed away.

          The Hong Kong-mainland express rail link - one of the world's most expensive infrastructure projects - was initially slated to cost HK$66 billion and is meant to strengthen the SAR's position as the transport hub in southern China.

          It was originally scheduled to have been completed this month, but was pushed back to late 2017, while its price tag was revised to HK$71.5 billion after MTR Corp was found to have kept the government in the dark about the delay.

          Chan Han-pan, chairman of the LegCo subcommittee on railways, said he was not optimistic about the project meeting its latest completion date. Tien said the final cost could exceed HK$90 billion.

          Work on the Hong Kong terminus has already been delayed by unforeseen excavation issues, while safety concerns over the roof vaulting over the world's biggest underground terminus have been raised.

          Tien said the public coffers and MTR Corp, in which the government holds a majority stake, could share cost overruns in the event of natural disasters causing delays. For example, when tunnel boring machines become water logged during a rainstorm.

          But, the corporation should shoulder the extra costs arising from poor management, he said.

          tim@chinadailyhk.com

          HK-mainland express rail faces new delays

          (HK Edition 06/27/2015 page6)

          主站蜘蛛池模板: 欧美亚洲另类制服卡通动漫| 午夜免费福利小电影| V一区无码内射国产| 成人午夜免费无码视频在线观看 | 99九九热久久只有精品| 国产三级视频网站| 精品视频国产香蕉尹人视频| 国产av黄色一区二区三区| 精品无码黑人又粗又大又长| 人妻精品动漫h无码| 丰满的少妇被猛烈进入白浆| 成年午夜无码av片在线观看| 人人玩人人添人人澡超碰| 欧美日韩在线亚洲二区综二| 亚洲综合在线一区二区三区| 久久精品女人的天堂av| 日韩丝袜欧美人妻制服| 国产免费久久精品99reswag| 人妻在厨房被色诱中文字幕| 欧美视频网站www色| av天堂久久精品影音先锋| 中文字幕av国产精品| 国内熟妇人妻色在线视频| 国产大学生自拍三级视频| 毛片亚洲AV无码精品国产午夜| 国产a在视频线精品视频下载| 国产亚洲无日韩乱码| 人妻av一区二区三区av免费| 隔壁老王国产在线精品| 蜜臀av片| 国产亚洲AV电影院之毛片| 日韩av无码免费播放| 91福利视频一区二区| 亚洲人成小说网站色在线| 国产av一区二区亚洲精品| 中文字幕日韩精品有码| 中国国产免费毛卡片| 成在线人午夜剧场免费无码| 色综合久久久久综合体桃花网| 无码国产欧美一区二区三区不卡| 亚洲AV无码专区亚洲AV桃|